This project has moved and is read-only. For the latest updates, please go here.

The problem of MonthlyDOWTrigger

Topics: Errors
May 10, 2016 at 9:43 AM
Edited May 10, 2016 at 9:52 AM
When I try to create a MonthlyDOWTrigger, I find that I can just leave the "weeks" control empty, when I click OK and everything looks good, and but if I try to save the task, it is an exception show: "(79,8):Weeks:"


Maybe just forget to check the value of "weeks" when click OK.
May 11, 2016 at 2:32 AM
Edited May 12, 2016 at 8:40 AM
Maybe because forget to assign true to monthlyOnWeekDropDown.RequireAtLeastOneCheckedItem in Microsoft.Win32.TaskScheduler.UIComponents.MonthlyTriggerUI.

Hope it will be helpful
May 14, 2016 at 12:23 AM
That was it. Fixed in 2.5.20
Marked as answer by dahall on 5/13/2016 at 4:37 PM