The problem of MonthlyDOWTrigger

Topics: Errors
May 10, 2016 at 8:43 AM
Edited May 10, 2016 at 8:52 AM
When I try to create a MonthlyDOWTrigger, I find that I can just leave the "weeks" control empty, when I click OK and everything looks good, and but if I try to save the task, it is an exception show: "(79,8):Weeks:"


Maybe just forget to check the value of "weeks" when click OK.
May 11, 2016 at 1:32 AM
Edited May 12, 2016 at 7:40 AM
Maybe because forget to assign true to monthlyOnWeekDropDown.RequireAtLeastOneCheckedItem in Microsoft.Win32.TaskScheduler.UIComponents.MonthlyTriggerUI.

Hope it will be helpful
Coordinator
May 13, 2016 at 11:23 PM
That was it. Fixed in 2.5.20